Title
Cannot add an overlap link to an operation that is complete.
Severity
Information message.
Data
1: Reference information of the source operation of the link.
2: Reference information of the target operation of the link.
Explanation
You are trying to add an overlap link to an operation that is complete. The application does not allow this action. All the predecessors of an operation that is complete must be complete too. With the requested link, the predecessor of the completed operation would take place after that operation. It would therefore generate a circuit in the graph.
To avoid this situation, the application has canceled the action.
Action
Create links before you perform follow-up on the plan.