Title
Fixed period end date later than planned horizon end date.
Severity
Information message, logged for the environment. Table: JOURNAL.
Data
No additional data.
Explanation
The length of the fixed scheduling period is not consistent with the SRP horizon breakdown. The fixed period and the planned horizon where the application manages WOs in regenerative mode overlap. This can disorganize the fixed scheduling period, because the SRP engine can delete the WOs in the overlapping time frame.
Action
Reduce the fixed scheduling period, or enlarge the firm and planned horizons.