Follow-up is not allowed because one of the previous operations is not complete.

Severity 

Information message.

Data 

List of the previous operations still to complete.

Explanation 

In the Planning application configuration window (OPTIONS > CONFIGURATION, Follow-up tab):

  • Option Prevent follow-up if a previous operation is not complete is active AND

  • There is at least one operation preceding the follow-up operation that is not complete. The follow-up mode may be remaining time, remaining quantity, in progress, percentage, or complete operation.

Action 

Either clear the Prevent follow-up if a previous operation is not complete check box, or complete the previous operations.

¿Le ha sido útil este artículo?

¡Qué bien!

Gracias por sus comentarios

¡Sentimos mucho no haber sido de ayuda!

Gracias por sus comentarios

¡Háganos saber cómo podemos mejorar este artículo!

Seleccione al menos una de las razones
Se requiere la verificación del CAPTCHA.

Sus comentarios se han enviado

Agradecemos su esfuerzo e intentaremos corregir el artículo