Title
Cannot split an operation that is in progress, advanced or complete.
Severity
Information message.
Data
Operation reference information.
Explanation
You cannot split an operation that is in progress, advanced or complete, because its production is either under way or finished. Splitting at this stage would desynchronize the plan and production.
The application has canceled the action.
Action
If you need to split operations, do so before you perform follow-up on these operations.