PL_0329

Modificado el Mie, 8 Abr a 10:11 A. M.

Title 

Allocation of reservation resource failed.

Severity 

Information message, logged for the environment. Table: JOURNAL.

Data 

Operation reference information.

Explanation 

Resource allocation failed for the operation. There is not limited resource available for this operation. 

This may occur if:

  • The limited resource allocation is not a scheduling constraint, and you are trying to superimpose a resource allocation plan on the current plan.

OR

  •  the constraints of the resource release phase make it impossible to position that phase before a resource reservation phase. Therefore, resource reservation is impossible.

As a result, the application has deallocated limited resources on all operations.

Action

Verify that there are enough limited resources.

Verify that it is possible to position all the release phases without exceeding the number of resources.

Reschedule the plan with the resource allocation constraint. If the problem persists, contact the help desk.

¿Le ha sido útil este artículo?

¡Qué bien!

Gracias por sus comentarios

¡Sentimos mucho no haber sido de ayuda!

Gracias por sus comentarios

¡Háganos saber cómo podemos mejorar este artículo!

Seleccione al menos una de las razones
Se requiere la verificación del CAPTCHA.

Sus comentarios se han enviado

Agradecemos su esfuerzo e intentaremos corregir el artículo