PL_0330

Modificado el Mie, 8 Abr a 10:15 A. M.

Title 

Allocation of reservation resource failed. You will have to run scheduling with the limited resource constraint.

Severity 

Information message, logged for the environment. Table: JOURNAL.

Data 

No additional data.

Explanation 

Limited resource allocation is complete, but some operations still do not have the limited resources they need. This may occur if:

  • Resource allocation is not a planning constraint, and you are trying to superimpose a resource allocation plan on the current plan.

OR

  • The constraints of the resource release phase make it impossible to position that phase before a resource reservation phase. Therefore, resource reservation is impossible.

As a result, the application has deallocated limited resources on all operations.

Action

Verify that there are enough limited resources.

Verify that it is possible to position all release phases without exceeding the number of limited resources.

Schedule the plan with allocation of the limited resources. If the problem persists, contact the help desk.

¿Le ha sido útil este artículo?

¡Qué bien!

Gracias por sus comentarios

¡Sentimos mucho no haber sido de ayuda!

Gracias por sus comentarios

¡Háganos saber cómo podemos mejorar este artículo!

Seleccione al menos una de las razones
Se requiere la verificación del CAPTCHA.

Sus comentarios se han enviado

Agradecemos su esfuerzo e intentaremos corregir el artículo