Title
Problem displaying operation links.
Severity
Information message.
Data
Reference information on operation 1 (the predecessor).
Reference information on operation 2 (the successor).
Explanation
When displaying links between operations, the application has found a link consistency problem between operations 1 and 2. Operation 2 is in the list of successors of 1, but the mirroring link of 2 to 1 is not present in the list of predecessors of 2. There is probably a data consistency problem.
Action
For data stability, save your changes and close the application. You can then reopen the Planning application and recall WIP.