PL_0464

Modificado el Lun, 13 Abr a 9:40 A. M.

Title 

The constraint on resource groups was relaxed for these operations.

Severity 

Information message.

Data 

List of the operations for which the application relaxed the constraint.

Explanation 

Further to some dynamic changes to the plan, the allocation of limited resources changed, but the change did not take account of the constraint on resource groups. To take this constraint into account, you need to:

  • Reschedule the plan with the Limited resources planning constraint.

OR

  •  Reallocate limited resources, using menu items OPTIMIZATION > RESOURCE ALLOCATION.

Action 

To make sure that the constraint on limited resource groups applies, you can add precedence links between some of the operations.

¿Le ha sido útil este artículo?

¡Qué bien!

Gracias por sus comentarios

¡Sentimos mucho no haber sido de ayuda!

Gracias por sus comentarios

¡Háganos saber cómo podemos mejorar este artículo!

Seleccione al menos una de las razones
Se requiere la verificación del CAPTCHA.

Sus comentarios se han enviado

Agradecemos su esfuerzo e intentaremos corregir el artículo