Title
The constraint on resource groups was relaxed for these operations.
Severity
Information message.
Data
List of the operations for which the application relaxed the constraint.
Explanation
Further to some dynamic changes to the plan, the allocation of limited resources changed, but the change did not take account of the constraint on resource groups. To take this constraint into account, you need to:
Reschedule the plan with the Limited resources planning constraint.
OR
Reallocate limited resources, using menu items OPTIMIZATION > RESOURCE ALLOCATION.
Action
To make sure that the constraint on limited resource groups applies, you can add precedence links between some of the operations.